On a busy fit-out, the route to a final exit can change twice before lunch. A corridor that was clear at the morning briefing becomes a temporary store for ductwork. A fire door is locked to protect new finishes. An emergency light is isolated while a ceiling grid is altered. None of these decisions is unusual in isolation, but together they can leave a building without a dependable means of escape.

The practical response is to treat means of escape as a live system for the whole programme. It is not a handover item to be corrected at the end, and it is not solely the concern of the fire safety specialist. It is a daily condition that the principal contractor, fit-out contractor and subcontractors must maintain while the building is in transition.

The handover trap

It is tempting to regard escape provisions as part of final commissioning. Final signage, emergency lighting, fire door adjustments and route clearances are all verified before occupation, so the logic goes that they can be dealt with once the dust has settled. The difficulty is that the building is occupied throughout the fit-out, even if only by the construction workforce and visitors. Routes must work today, not only on the day the certificate is issued.

Under the Regulatory Reform (Fire Safety) Order 2005, the responsible person must maintain general fire precautions in occupied premises. During construction and refurbishment, CDM 2015 also places duties on those who control the site. The practical implication is straightforward: if a route is compromised on a Tuesday morning, a completed handover pack on Friday does not resolve the risk.

Establish the route strategy before ordering signage

Before partitions are erected or ceilings are opened, the project team should agree which routes will remain available at each stage. That means identifying primary and alternative escape routes, final exits, stair cores, corridors and the assembly point. It also means recording where temporary routes will be needed when final routes are obstructed.

A route strategy should be drawn, not assumed. It should show the proposed sequence of works and the points at which routes change. The strategy should name who authorises a change and who checks that it has been implemented. On larger schemes, that may sit with a fire safety coordinator; on smaller fit-outs, it may be the site manager. The important point is that ownership is clear and changes are not made informally by subcontractors.

Temporary signage must work at decision points

Temporary signage is often treated as a low-cost fix, but its purpose is critical. Signs should be positioned at every point where a person must choose a direction, not merely at the final exit. They should be legible from a reasonable distance, mounted consistently and kept free of obstruction. Handwritten paper notices taped to a hoarding are unlikely to withstand a busy site, and they may conflict with other signs.

Where the route changes, the signage should change on the same day. It is better to use standard fire exit signs with clear directional arrows than improvised wording. If a temporary route passes through an unfamiliar area, additional signs may be needed to prevent people from continuing along a route they used previously. Signage should also be checked after any new partition or stack of materials is introduced.

Lighting the route when final systems are not ready

Escape routes need adequate lighting, including emergency lighting where required. During fit-out, the final emergency lighting system may not be commissioned, and normal lighting may be isolated for ceiling or service works. Temporary self-contained luminaires or battery-backed units can bridge the gap, but they must be tested and maintained.

Daylight and borrowed light from adjacent areas should not be relied upon. A corridor that appears well lit at midday may be dark when doors are closed or temporary partitions are installed. Stairwells, corridors, final exits and changes of level deserve particular attention. Where exit signs are illuminated, confirm that the illumination remains effective. A short recorded check of temporary lighting is more useful than an assumption that the electrician has dealt with it.

Doors and hardware: secure without trapping

Fire doors and final exit doors are frequently disturbed during fit-out. Contractors may lock doors to protect new finishes, remove closers to move materials, or wedge doors open for access. Each of these actions can undermine the escape route.

Temporary security should not prevent escape from the inside. Final exit doors must remain openable without a key or specialist knowledge. Fire doors should not be wedged open unless they are held by an approved device linked to the fire alarm system. If a door is incomplete or temporarily fitted, the route strategy should account for it. Daily checks should include handles, closers, locks, thresholds and any obstruction that prevents full opening.

Clear widths and the accumulation problem

The most common failure on a live fit-out is not a missing sign or a faulty light. It is accumulation. Pallets of plasterboard, bins, offcuts, cable drums and protective wrapping all find their way into corridors because they are convenient. Over a few days, a route that was designed with adequate width can become a single-file passage.

Design clear widths should be protected, not eroded. Floor markings can help, but they only work if they are enforced. Waste should be removed on a schedule that reflects the pace of work, not only when the skip is full. Materials should have designated storage areas away from escape routes. If a temporary partition reduces a corridor, the route strategy should be reviewed before it is installed, not after.

Daily checks and change control

A short, recorded walk of the escape routes at the start of the working day is one of the most effective controls available. The check need not be elaborate. It should confirm that signs are visible, lighting is working, doors operate correctly, routes are clear and no new obstruction has appeared. Any defect should be logged and closed out, with a clear escalation route if it cannot be resolved immediately.

Change control is equally important. A new partition, a service isolation, a locked door or a change in storage arrangements can all affect means of escape. The team should treat each of these as a trigger for review. Subcontractors should be briefed at induction and reminded at coordination meetings that escape routes are not storage areas and that changes to doors or lighting require authorisation.

Evidence from day one

At completion, the final escape provisions will be verified as part of handover. That verification is necessary, but it should not be the first time the route has been inspected. Temporary route drawings, daily check records, lighting tests, signage changes and door hardware checks all form a useful trail. They show that means of escape was actively managed during the works, not simply restored at the end.

A fit-out is a sequence of temporary conditions. The means of escape must be designed, checked and maintained through every one of them. Treated as a live system, it remains dependable while the building changes around it.

All Articles

Related Articles

Evidence at Every Crossing: Making Fire Stopping Inspectable on UK Fit-Outs

Evidence at Every Crossing: Making Fire Stopping Inspectable on UK Fit-Outs

Closing the Gap: Fire Door Verification on UK Commercial Fit-Outs

Closing the Gap: Fire Door Verification on UK Commercial Fit-Outs

Capacity Before Carpentry: Locking Utility Connections into the Fit-Out Programme

Capacity Before Carpentry: Locking Utility Connections into the Fit-Out Programme